Title: |
Letter to Nathan Nadler re: Construction Status Report D- 3, For the month of June, Project number DOS-8376, project title: Government House East Wing Renovation |
|
Series Title: |
Historic St. Augustine: East Wing Restoration, Haas House |
|
Physical Description: |
Correspondence |
|
Language: |
English |
|
Publication Date: |
1984 |
|
Physical Location: |
Box: | 8 | Divider: | Government House Maintenance | Folder: | East Wing Restoration, Haas House |
|
Subjects |
|
Subject: |
Saint Augustine (Fla.) 48 King Street (Saint Augustine, Fla.) Government House (Saint Augustine, Fla.) |
|
Spatial Coverage: |
North America -- United States of America -- Florida -- Saint Johns -- Saint Augustine -- 48 King Street |
|
Coordinates: |
29.892465 x -81.313142 |
Record Information |
|
Bibliographic ID: |
UF00095487 |
|
Volume ID: |
VID00005 |
|
Source Institution: |
University of Florida |
|
Holding Location: |
University of Florida |
|
Rights Management: |
All rights reserved by the source institution and holding location. |
|
STATE OF FLORIDA
DEPARTMENT OF
GENERAL SERVICES
Larson Building, Tallahassee 32301
Ronald W. Thomas, Executive Director
Date March 26, 1984
Clay Stratton, Contractor
208 St. George Street
St. Augustine, Florida 32084
NOTICE TO MOBILIZE ON SITE AND TO
DIVISIONS
ADMINISTRATION INFORMATION
BOND FINANCE SERVICES
BUILDING CONSTRUCTION MOTOR POOL
AND PROPERTY MANAGEMENT PURCHASING
COMMUNICATIONS SECURITY
SURPLUS PROPERTY
Please address reply to: 512 Larson Building
CERTIFIED MAIL-RETURN RECEIPT REQUESTED
"PLEASE ATTACH TO YOUR CONTRACT
PROCEED WITH CONSTRUCTION
RE: Project No. DOS-8375-A/8376-A
Haas House Renovation & Installation
of Concrete Floor Slab at Government
House East Wing
Gentlemen: St. Augustine, Florida
Please consider this letter as your formal NOTICE TO MOBILIZE ON SITE AND TO PROCEED
WITH CONSTRUCTION of the contract work. It establishes April 2, 1984
as your contract commencement time and May 31, 1984 as the required date
of substantial completion. Please contact the Architect/Engineer before starting
construction on this project.
Mr. Nathan Nadler is the State's Project Director and will represent the
Owner in matters pertaining to the project. Enclosed is a guide to aid you in the
construction phase of this project.
An Initial Construction Conference will be scheduled by the Project Director, and the
Architect/Engineer. Please bring this guide, as well as a list of questions, if any,
to this conference. The conference is not a prerequisite to commencing work on the
project.
We look forward to a pleasant association.
Ve truly yours,
ack C. Koons, Administrato
Project Development Section
JCK/la
Enclosures: Construction Guide
xc: Comptroller
Project Director
Using Agency Repr. -Hector Miron v
Using Agency F&A-Lee Warner
Architect
Administrator (Design & Evaluation)
Mr. John Dixon
Bureau of Apprenticeship
(Letter)
"t
Georqe Firestone
Secretary of State
Doyle Conner
Commissioner of Anriculture